  151   14 Oct 2020 08:39 Tom ThorpeRoutineGeneralLog regarding MB2 removal from Proto-0Drive folder with data files and some pictures:  https://drive.google.com/drive/folders/1Sr27kQTOO2kciBY7v-wYBP06tWLVEjiP

Lab notes @ CERN

11/10/2020
 forward_warm_1.pngiv_warm_1.pngiv_warm_2.png 
  49   28 Oct 2019 08:33 Ben SmithProblem FixedSoftwareNeed python3 package tkinter on DAQ pcI have installed the python3-tkinter package
from yum. I checked that "import tkinter"
works from a python3 prompt.
  
  50   28 Oct 2019 14:10 Ben SmithProblem FixedSoftwareConverters installed in VME crate> V1725 board #0 logic level is set to TTL
(boards #1, #2, #3 to NIM) 
  
  53   01 Nov 2019 06:07 Ben SmithProblem FixedSoftwareRestoration of network settingsFor a few days we were unable to access ds-proto-daq
remotely. We were also unable to reach the
outside world from ds-proto-daq.
  
  54   01 Nov 2019 06:15 Ben SmithProblem FixedSoftwareRestoration of elogAfter booting, the elog was only showing logs
from before July, and was missing the "For
Shifters" category. It appears we were loading
  
  89   06 Nov 2019 12:28 Ben SmithProblem FixedGeneralEvening data taking, purity check> Not sure if the trigger threshold is correctly
set, there is an error:
  
  95   08 Nov 2019 02:21 Ben SmithProblem FixedSoftwareIncreased max waveform length that we can takeI've increased various thresholds so that
we can now take 3000us (3ms) waveforms.
  
  105   09 Nov 2019 07:29 Marco RescignoProblem FixedMIDASthis morning problemfrontend process still alive but slow,
causing lot of rejected triggers.

stopped and restarted the feov1725
  
  114   11 Nov 2019 00:47 Yi / EdgarProblem FixedDigitizerProblem fixed by restarting the VME crate    
  118   11 Nov 2019 23:57 Yi WangProblem FixedTriggerID 117 problem is fixedThe problem reported in ID 117 is somehow
fixed this morning.
  
  12   08 Feb 2019 12:08 ThomasProblemHardwareInstalled Marco's A3818; didn't workI installed Marco's A3818 PCIe card.  Didn't
seem to work.  I got communication errors
talking to link 2.  The
  
  13   13 Feb 2019 16:45 PierreProblemHardwareA3818 from MarcoChecking again Marco's A3818:
- Port #2 (third from top of card) is acting
up.
  
  33   12 Jul 2019 02:05 Marco RescignoProblemTriggerMB1 test in proto-0 setup/1Tried to get laser sync signal into chronobox
(clkin1 input), apparently all triggers dropped
by chronobox
  
  40   16 Jul 2019 02:41 Marco RescignoProblemTriggerBusy handlingThis morning tried to get some data with
Vbias=65 V, which seems better for the SiPM
in MB1.
  
  46   26 Oct 2019 07:33 Sam HillProblemSoftwareTest of IV ScriptPeople:  Simone, Sam, Tom, Edgar

Tested IV curve python script that
runs using MIDAS. Measured resistance consistant
 IV_curve_29K.png 
  48   28 Oct 2019 06:28 Simone StrackaProblemSoftwareNeed python3 package tkinter on DAQ pcWe need python3 package tkinter installed
on ds-proto-daq in order to run the steering
module GUI. 
  
  51   28 Oct 2019 14:56 Simone StrackaProblemSoftwareIssues with network configuration for steering moduleWe have tried to connect the steering module
to the DAQ pc via Luigi's USB-Ethernet
adapter. 
  
  112   10 Nov 2019 12:15 E. SanchezProblemMIDASProblem DAQError during data taking  1573416708
21:11:48.151 2019/11/10 [feov1725MTI00,INFO]
V1725 PLL loss lock Board:0 (vmeAcq=0x0)
  
  113   11 Nov 2019 00:37 Yi WangProblemMIDAScannot connect to rootanaThe connection to rootana is lost.

No data taking can be started.
  
  117   11 Nov 2019 10:05 Sam HillProblemGeneralEvening data takingAttemted the following run, and
it started but the rate was shoing 0 and
it got stuck on 5 events
  