9
|
31 Jan 2019 15:18 |
Pierre | Configuration | Trigger | Trigger rate | Somehow the trigger rate was not matching
the trigger source.
Find out that Link 3 was not collecting and |
|
10
|
06 Feb 2019 14:12 |
Pierre | Configuration | Hardware | Extended Trigger Time Tag (ETTT) | Confirmed this ETTT configuration is working.
ETTT Enabled [22..21] |
|
13
|
13 Feb 2019 16:45 |
Pierre | Problem | Hardware | A3818 from Marco | Checking again Marco's A3818:
- Port #2 (third from top of card) is acting
up.
|
|
22
|
27 Mar 2019 08:57 |
Pierre | Configuration | Hardware | CERN setup | Found that the Trigger out from the CB is
on output1
Trigger / Not used
|
|
23
|
27 Mar 2019 14:04 |
Pierre | Configuration | Trigger | Time stamp sync | The ChronoBox latest FW is loaded. Let tme
know if this is what the chronobox should
look like in term of registers.
|
|
24
|
28 Mar 2019 02:18 |
Pierre | Configuration | Trigger | Test | |
|
14
|
19 Feb 2019 16:26 |
Pierre-A. | Configuration | General | Overall HW configuration | For Reference,
I put a simple schematic for the
Trigger/Run control. |
|
90
|
07 Nov 2019 02:07 |
Sam | Routine | General | Run 963 Laser Run with SiPMs at 65V, 12us trace | Laser Intensity: MAX
Threshold: external
clock (laser NIM), laser set to 1kHz |
|
92
|
07 Nov 2019 02:16 |
Sam | Routine | General | Run 964 Laser Run with SiPMs at 65V, 30us trace | Laser Intensity: MAX
Threshold: external
clock (laser NIM), laser set to 1kHz |
|
93
|
07 Nov 2019 02:34 |
Sam | Routine | General | Run 966 Laser Run with SiPMs at 65V, 30us trace | Laser Intensity: MIN
Threshold: external
clock (laser NIM), laser set to 1kHz |
|
46
|
26 Oct 2019 07:33 |
Sam Hill | Problem | Software | Test of IV Script | People: Simone, Sam, Tom, Edgar
Tested IV curve python script that
runs using MIDAS. Measured resistance consistant |
|
106
|
09 Nov 2019 09:39 |
Sam Hill | Routine | General | Evening data taking | Run 1016
Gas pocket: ON
(thinkness 7mm) |
|
116
|
11 Nov 2019 09:31 |
Sam Hill | Routine | General | Afternoon system monitoring: IV curves and Dewar refill | 17:30
Took a set of IV curves using 0.5V
steps from 30-50V and 0.05 steps above 50V. |
|
117
|
11 Nov 2019 10:05 |
Sam Hill | Problem | General | Evening data taking | Attemted the following run, and
it started but the rate was shoing 0 and
it got stuck on 5 events |
|
148
|
20 Nov 2019 04:47 |
Sam Hill | Routine | General | IV Curve - warming up | Temp at start:
A: 242.7K B: 278.16K
C: 86.4K D: 240.89K |
|
44
|
25 Oct 2019 07:17 |
Simone Stracka | Routine | Hardware | Photoelectronics activities on October, 24 | Crew: Edgar Sanchez Garcia, Sam Hill, Simone
Stracka, Tom Thorpe, Yi Wang
Morning: Tested photocurrents for |
|
45
|
25 Oct 2019 07:44 |
Simone Stracka | Routine | Hardware | MB2 activities on October 25 | Crew: Edgar Sanchez Garcia, Sam Hill, Simone
Stracka, Tom Thorpe, Yi Wang
|
|
47
|
27 Oct 2019 06:08 |
Simone Stracka | Configuration | Hardware | Converters installed in VME crate | People: Edgar, Simone
Installed differential to single-ended
converters in VME crate, and turned crate |
|
48
|
28 Oct 2019 06:28 |
Simone Stracka | Problem | Software | Need python3 package tkinter on DAQ pc | We need python3 package tkinter installed
on ds-proto-daq in order to run the steering
module GUI. |
|
51
|
28 Oct 2019 14:56 |
Simone Stracka | Problem | Software | Issues with network configuration for steering module | We have tried to connect the steering module
to the DAQ pc via Luigi's USB-Ethernet
adapter. |
|