ID Date Author Typedown Category Subject
  23   17 Nov 2019 00:45 Yi WangProcedure/OperationCooling Systemopen dewar refill

09:45 am open dewar refill to full, TPC pressure 31 mbar

  24   18 Nov 2019 02:04 Yi WangProcedure/OperationCooling SystemOpen dewar refill

9:00 am open dewar refilled to full, TPC pressure 30 mbar

  13   11 Nov 2019 04:08 Yi WangProblemCooling SystemPossible power blackout on Nov 9

There was a possible power blackout on Nov 9 from 2 am to 4 am at builidng 182.

During the blackout, the vacuum pump for pumping the insulation vacuum of the cryogenic system was OFF.

Moistures were accumulated in the interlayer during these two hours, and now the vacuum insulation is not as good as before.

This causes some bubbles generating in the liquid delivery bellow and significantly reduces the fast recirculation speed.